Case Study

Hoe Valley School & Woking Sportsbox

wOKING, Surrey

The Hoe Valley School contract comprised the main school; the Woking Sportsbox, a trackside stadium with free-standing grandstand and equipment stores.

A2O were appointed to install an insulated Western Red Cedar rainscreen cladding system.

WILLMOTT DIXON CONSTRUCTIon

"You have performed above our standard and have exceeded WD Construction Cobham’s expectations. Please keep to these high standards and where you feel you can, improve on them, a very well done from us all. So far we have been impressed with A2O's performance."

Placeholder - Placeholder
Formal Customer Feedback

Challenges

The local Council was very concerned about the quality of the timber, and wanted a knot-free specification.

The challenge was how to support the timber rainscreen whilst accommodating insulation to achieve the target U-value.

 

The Council and Main Contractor demanded very high quality standards. A full design service was required, covering all interface details to ensure the installers achieved a high quality finish on site.

The timber cladding support for the Grandstand had to be custom built.

Solutions

A2O arranged a meeting with timber supplier Norclad to reassure the Council representatives on the quality of the materials.

A2O designed a hybrid aluminium and timber support system for the timber rainscreen. This system ensured water drainage, air flow and adjustment, to suit accurante interfaces with brickwork and glazing.

On World Quality Day, Willmott Dixon held a Quality Day for their site managers at Hoe Valley. Site Manager David Sweeney presented a quality award to Deividas Bardauskas for A2O.

Bespoke details ensured a good fit and accurate interfaces.

Fact File

Sector

STATUS

Value

Scope of Work